|
STS-9 |
Columbia |
October 19, 1983 |
|
|
Columbia was rolled back to the VAB, de-stacked, and the orbiter returned
to the Orbiter Processing Facility because of a suspect exhaust nozzle on
the right solid rocket booster. |
|
STS 41-D |
Discovery |
July 11,
1984 |
|
|
Discovery was rolled back to the VAB following a pad abort on June 26. The
vehicle was returned to the VAB, de-stacked, and the orbiter returned to
the Orbiter Processing Facility to remove and replace the number three
main engine which caused the abort. |
|
STS
51-E/51-B |
Challenger |
March 5, 1985 |
|
|
Challenger was rolled back due to a timing problem with the primary
payload, the Tracking and Data Relay Satellite-B. The vehicle was
de-stacked in VAB and the orbiter returned to Orbiter Processing Facility.
This mission, 51-E, was cancelled and the orbiter re-manifested with 51-B
payloads. |
|
STS-35 |
Columbia |
June 12, 1990 |
1st rollback. |
|
Columbia was rolled back twice during preparations for mission STS-35. The
first time occurred after a hydrogen leak was detected in the external
tank/orbiter 17-inch umbilical. |
|
STS-38 |
Atlantis |
August 9, 1990 |
|
|
Atlantis was rolled back to the VAB after tests confirmed a hydrogen fuel
leak on the external tank side of the external tank/orbiter 17-inch quick
disconnect umbilical. The vehicle was de-stacked. |
|
STS-35 |
Columbia, |
October 9, 1990 |
2nd rollback. |
|
Columbia was rolled back a second time due to the threat of severe weather
from Tropical Storm Klaus. |
|
STS-39 |
Discovery |
March 7, 1991 |
|
|
Discovery rolled back to the VAB after significant cracks were found on
all four lug hinges on the two external tank umbilical door drive
mechanisms. The vehicle was de-stacked. |
|
STS-68 |
Endeavour |
August 24, 1994 |
|
|
Endeavour was rolled back to the VAB after a pad abort due to an
unacceptably high discharge temperature in the high-pressure oxidizer
turbo pump on main engine number three. All three engines were replaced in
the VAB. |
|
STS-70 |
Discovery |
June 8, 1995 |
|
|
Discovery was rolled back to the VAB after Yellow Flicker Woodpeckers
drilled about 195 holes on the external tank foam insulation, many of
which were too high up on the tank to be accessed at the pad for repairs. |
|
STS-69 |
Endeavour |
August 1, 1995 |
|
|
Endeavour was rolled back to the VAB due to the threat of severe weather
from Hurricane Erin which passed through Brevard County where the Kennedy
Space Center is located. |
|
STS-79 |
Atlantis |
July 10, 1996 |
|
|
Atlantis was rolled back to the VAB due to the threat of severe weather
from Hurricane Bertha. |
|
STS-79
|
Atlantis |
September 4, 1996 |
|
|
Atlantis was rolled back to the VAB due to the threat of severe weather
from Hurricane Fran. |
|
STS-96 |
Discovery |
May 16, 1999 |
|
|
Discovery was rolled back to the VAB to repair hail damage to the external
tank foam insulation. |
|
STS-98 |
Atlantis |
January 2, 2001 |
1st
rollback. |
|
Atlantis began rollout
to Launch Pad 39A, but an hour later stopped on the crawler path so
engineers could troubleshoot a failed computer processor on the crawler
transporter. Troubleshooting efforts were unsuccessful, so managers
decided to roll Atlantis back into VAB high bay 3 using a secondary
computer processor. |
|
STS-98 |
Atlantis |
January 19, 2001 |
2nd
rollback. |
|
Atlantis was rolled
back to the VAB due to uncertainty involving the integrity of the SRB
cables. |
| Source:
Kennedy
Space Center |